High Court Of Karnataka|28 March, 2019
|

JUDGMENT / ORDER

IN THE HIGH COURT OF KARNATAKA AT BENGALURU DATED THIS THE 28TH DAY OF MARCH 2019 BEFORE THE HON’BLE MR. JUSTICE ALOK ARADHE WRIT PETITION NO.28080 OF 2018(GM-RES) BETWEEN:
SOUTH WESTERN RAILWAY REPRESENTED BY THE DIVISION RAILWAY MANAGER(WORKS) BANGALORE DIVISION SOUTH WESTERN RAILWAY 3RD FLOOR, DIVISIONAL OFFICE MAJESTIC, BANGALORE – 560 023.
… PETITIONER (BY MR.VISHNU HEGDE, ADV.) AND:
1. THE CHIEF ENGINEER GOVERNMENT OF KARNATAKA DR.AMBEDKAR ROAD VIDHANA SOUDHA BANGALORE – 560 001.
2. THE SUPERINTENDENT OF POLICE GOVERNMENT RAILWAY POLICE BEHIND RESERVATION COMPLEX CITY RAILWAY STATION BANGALORE – 560 023.
3. THE DEPUTY COMMISSIONER OF POLICE GOVERNMENT RAILWAY POLICE BEHIND RESERVATION COMPLEX CITY RAILWAY STATION BANGALORE – 560 023.
4. THE RAILWAY POLICE SUB-INSPECTOR(RPS) GOVERNMENT RAILWAY POLICE, (GRP) PLATFORM NO.1, YESHWANTPUR RAILWAY STATION BANGALORE – 560 022.
PRESENTLY MR. BIRADHAR.
… RESPONDENTS (BY MR.Y.D.HARSHA, LEARNED HCGP) THIS WRIT PETITION IS FILED UNDER ARTICLES 226 & 227 OF THE CONSTITUTION OF INDIA, PRAYING TO DIRECT THE RESPONDENT NO.1 AND 3 TO CONSIDER THE REPRESENTATIONS OF THE PETITIONER DATED: 26.06.2018 I.E., ANNEXURE-A, B AND C AND FURTHER DIRECT THE RESPONDENTS NOT TO CARRY ANY UNLAWFUL AND ILLEGAL CONSTRUCTION IN THE SCHEDULE PROPERTY.
THIS WRIT PETITION COMING ON FOR PRELIMINARY HEARING IN ‘B’ GROUP THIS DAY, THE COURT MADE THE FOLLOWING:-
ORDER In this petition, the petitioner inter alia seeks a direction to the respondent Nos.1 to 3 to consider the representations dated 26.06.2018 contained in Annexures A, B and C submitted by the petitioner and to take suitable action in accordance with law.
2. Accordingly, I deem it appropriate to dispose of the writ petition with a direction that suitable action on the representations submitted by the petitioner, if not already decided shall be taken in accordance with law by the competent authority by a speaking order within four months from the date of receipt of certified copy of the order passed today. It is made clear that this Court has not expressed any opinion on the merits.
Accordingly, the petition is disposed of.
Sd/- JUDGE SS
Disclaimer: Above Judgment displayed here are taken straight from the court; Vakilsearch has no ownership interest in, reservation over, or other connection to them.
Title

South Western Railway vs The Chief Engineer Government Of Karnataka And Others

Court

High Court Of Karnataka

JudgmentDate
28 March, 2019
Judges
  • Alok Aradhe