[Order of the Court was made by K.K.SASIDHARAN, J.] Since follow up action was not taken by the fourth respondent, after issuing notice under Section 6 of the Tamil Nadu Land Encroachment Act, the petitioner has come up with the present Writ Petition.
2.We direct the fourth respondent to take follow up action pursuant to the notice issued by him for removal of encroachment, after issuing notice to the respondents 7 to 11. We make it clear that the issue shall be considered by the fourth respondent on merits and as per law, after affording reasonable opportunity to the encroachers. Such exercise shall be completed within a period of three months from the date of receipt of a copy of this order.
3.The writ petition is disposed of with the above direction. No costs.
To
1.The District Collector, Sivagangai District, Sivagangai.
2.The Director of Planning, Sivagangai District, Sivagangai.
3.The Revenue Divisional Officer, Revenue Divisional Office, Devakottai, Sivagangai District.
4.The Tahsildar, Devakottai Taluk Office, Devakottai, Sivagangai District.
5.The Block Development Officer, Devakottai Taluk, Devakottai, Sivagangai District.
.
Disclaimer: Above Judgment displayed here are taken straight from the court; Vakilsearch has no ownership interest in, reservation over, or other connection to them.
Title

R.M.Karmegam Thevar Ambalam vs The District Collector

Court

Madras High Court

JudgmentDate
01 August, 2017