Mr.O.Selvam, learned Government Advocate takes notice for the first respondent and Mr.S.K.Rameshwar, learned counsel takes notice for respondents 2 and 3.
2.Seeking to forbear the respondents from erecting, drawing any High Tension Electricity Towers or Lines in the petitioner's lands bearing S.F.No.482/2 of Kallipalayam, Kozhumanguzhi Village, Dharapuram Taluk, Tiruppur District, the petitioner has filed the present writ petition.
3.It appears that the matter is pending before the District Magistrate/District Collector, Tiruppur, under
Section 16 of the Indian Telegraph act, 1885. In such view of the matter, the said authority viz., the first respondent is directed to pass appropriate orders on the same, after due notice to the parties concerned, within a period of six weeks from the date of receipt of a copy of this order. Needless to state that till then, status quo as on today shall be maintained.
4.With the above direction, the writ petition stands disposed of. No costs. Consequently, connected miscellaneous petition is closed.
29.06.2017 Index:Yes/No mmi To
1.The District Collector, Tiruppur District, Tiruppur.
2.The Superintending Engineer, General Construction Circle, TANTRANSCO, Dr.Subbarayan Road, Tatabad, Coimbatore 12.
3.The Executive Engineer, General Construction Circle, TANTRANSCO, Ellamedu, Ingur, Perundurai Taluk, Erode District.
M.M.SUNDRESH, J.
mmi W.P.No.16249 of 2017 29.06.2017