HONOURABLE SRI JUSTICE P. NAVEEN RAO WRIT PETITION No. 32643 of 2014 Date :5.12.2014 Between :
N Munappa @ Muni Reddy S/o Late Hanamanthu R/o Kistampally village, Narva Mandal, Mahaboobnagar district & others … Petitioners and State of Telangana, Rep by its Principal Secretary (I & CAD) Secretariat, Hyderabad and others … Respondents The Court made the following:
HONOURABLE SRI JUSTICE P. NAVEEN RAO WRIT PETITION No. 32643 of 2014 ORDER:
Land belonging to the petitioners to an extent Ac.0.02½, Ac.0.02 and Ac.0.02 cents respectively in survey No. 138/2, Nandimalla Sivar, Atmakur Mandal, Mahaboobnagar district was acquired by following due procedure of law contemplated under Land Acquisition Act, 1894 for the purpose of Priyadarshini Jurala Project. Award No. 11 of 2001 dated 03.02.2001 was passed fixing the compensation of Rs.36,000/- per acre payable to the petitioners. Properties and lands of several persons were acquired in similar manner. Some of the oustees claimed for enhancement of compensation. Their claim was referred to Civil Court. In O.P. No.11 of 2004 and batch, Senior Civil Judge, Gadwal, allowed the claim for higher compensation. After order passed by the Senior Civil Judge in O P No. 11 of 2004, petitioners have applied for redetermination of the compensation under Section 28-A of the Act. The Land Acquisition Officer, vide orders dated 24.4.2014 redetermined the compensation payable in accordance with Section 28-A of the Act. Grievance of the petitioners necessitating institution of this writ petition is, though revised compensation is determined as early as on 24.4.2014, so far the differential amount of Rs.39,858/- to first petitioner, Rs.31,887/- to second petitioner and Rs.31,887/- to third petitioner is not paid and the same is causing undue hardship and suffering to the petitioners.
2. On instructions, learned Assistant Government Pleader for Irrigation submits that respondents require three months time to deposit the amount as determined by the Land Acquisition officer vide order dated 24.4.2014.
3. Having regard to the fact that the property of the petitioners was acquired in the year 2001 and though Land Acquisition Officer re-determined compensation at higher rate on 24.4.2014, but without any justifiable reason the amount is not paid to the petitioners so far, third respondent is directed to take steps to deposit the amount payable to the petitioners as quantified by the Land Acquisition Officer within eight weeks from the date of receipt of copy of the order and on such deposit, the 4th respondent-Special Deputy Collector (Land Acquisition) is directed to take steps to release the same to the petitioners.
Accordingly the writ petition is disposed of. No Costs. Having regard to the same, all old miscellaneous petitions are closed.
P NAVEEN RAO,J DATE:5.12.2014 TVK HONOURABLE SRI JUSTICE P. NAVEEN RAO WRIT PETITION No. 32643 of 2014 Date :5.12.2014
Disclaimer: Above Judgment displayed here are taken straight from the court; Vakilsearch has no ownership interest in, reservation over, or other connection to them.
Title

N Munappa @ Muni Reddy vs State Of Telangana And Others

Court

High Court Of Telangana

JudgmentDate
05 December, 2014
Judges
  • P Naveen Rao