Mr N Dhanaraj And Others vs The Bangalore Electricity Executive Supply Company And Others

High Court Of Karnataka|10 April, 2019
|

JUDGMENT / ORDER

IN THE HIGH COURT OF KARNATAKA AT BENGALURU DATED THIS THE 10TH DAY OF APRIL, 2019 BEFORE:
THE HON’BLE MRS. JUSTICE S.SUJATHA W.P.Nos.12742 & 13743 – 13746/2019 (GM – KEB) BETWEEN:
1. Mr. N.DHANARAJ S/O LATE NAGA AGED ABOUT 34 YEARS 2. Mr. N.PRAKASH S/O LATE NAGA, AGED ABOUT 32 YEARS BOTH ARE R/O NO.45/5-1, 8TH MAIN, KASTURBA NAGAR, ASWATHKATTE MAIN ROAD, BANGALORE-560026 ... PETITIONERS [BY SMT.LALITA P.M., ADV. FOR SRI MOHAN KUMAR K.T., ADV.] AND:
1. THE BANGALORE ELECTRICITY EXECUTIVE SUPPLY COMPANY K.R.CIRCLE, Dr. B.R.AMBEDKAR VEEDHI, BANGALORE-560 001 2. THE EXECUTIVE ENGINEER (ELE) BESCOM, RAJARAJESHWARINAGAR DIVISION, B.R.PURA, BANGALORE-560026 3. THE ASSISTANT EXECUTIVE ENGINEER (ELE) W1 SUB-DIVISION, AVALAHALLI, 50 FEET ROAD, BSK III STAGE, BANGALORE-560085 …RESPONDENTS [BY SRI H.V.DEVARAJU, ADV.] THESE WRIT PETITIONS ARE FILED UNDER ARTICLES 226 & 227 OF THE CONSTITUTION OF INDIA, PRAYING TO DIRECT THE R-2 AND 3 TO CONSIDER THE PETITIONERS APPLICATION DATED 31.10.2018 (ANNEXURE-G) AND TO PROVIDE PERMANENT ELECTRICITY SUPPLY TO THE SCHEDULE PROPERTY.
THESE PETITIONS COMING ON FOR PRELIMINARY HEARING IN ‘B’ GROUP, THIS DAY, THE COURT MADE THE FOLLOWING:-
O R D E R The petitioners are aggrieved by the inaction of the respondents in not considering the application/representation dated 31.10.2018 at Annexure – C submitted by the petitioners to provide permanent electricity supply to the property bearing Municipal No.9 (Old No.852) measuring east to west (51+53)/2 feet, north to south 30 feet, with building standing thereon, situated at 9th Main Road, Sringar, Banashankari 1st Stage, Bengaluru.
2. It is the contention of the petitioners that an application has been submitted on 31.10.2018 by the petitioners seeking new electricity connection. Despite several requests made, the same has not been considered, which has caused irreparable hardship, injury and loss to the occupants of the said building in question.
3. Considering the totality of circumstances of the case, this Court is of the considered opinion that there is no impediment for respondent Nos.2 and 3 to consider the petitioners’ application at Annexure – G in accordance with law and take a decision.
4. Hence, respondent Nos.2 and 3 are directed to consider the application of the petitioners dated 31.10.2018 at Annexure – G and take a decision in accordance with law in an expedite manner, in any event, not later than eight weeks from the date of receipt of the certified copy of the order.
With the aforesaid observations and directions, these writ petitions stand disposed of.
Sd/- JUDGE PMR
Disclaimer: Above Judgment displayed here are taken straight from the court; Vakilsearch has no ownership interest in, reservation over, or other connection to them.
Title

Mr N Dhanaraj And Others vs The Bangalore Electricity Executive Supply Company And Others

Court

High Court Of Karnataka

JudgmentDate
10 April, 2019
Judges
  • S Sujatha