High Court Of Judicature at Allahabad|28 February, 2019
|

JUDGMENT / ORDER

Court No. - 28
Case :- WRIT - A No. - 3196 of 2019 Petitioner :- Dayaram Respondent :- Up State Bridge Corporation Ltd. Through Its Md, Lucknow. And 4 Others Counsel for Petitioner :- Pramod K. Gupta Counsel for Respondent :- Mukesh Kumar Kushwaha,Manish Goyal Hon'ble Rohit Ranjan Agarwal,J.
Heard Sri Pramod Kumar Gupta, learned counsel for the petitioner, Sri M.K.Kushwaha, learned counsel for respondent nos.1 to 4 and Sri Anil Kumar Goswami, learned counsel for respondent no.5.
The petitioner attained the age of superannuation on 30.6.2018, but till date his retiral dues has not been paid by the respondents neither he has received the benefit of 7th Pay Commission. In this regard he has moved a representation on 11.1.2019.
In view of the above, the writ petition is disposed of with the direction to respondent no.1 to consider and decide the representation of the petitioner by a reasoned and speaking order expeditiously, preferably within a period of three months from the date of production of a certified copy of this order.
Order Date :- 28.2.2019 AKJ
Disclaimer: Above Judgment displayed here are taken straight from the court; Vakilsearch has no ownership interest in, reservation over, or other connection to them.
Title

Dayaram vs Up Bridge Corporation Ltd Through Its Md

Court

High Court Of Judicature at Allahabad

JudgmentDate
28 February, 2019
Judges
  • Rohit Ranjan Agarwal
Advocates
  • Pramod K Gupta