Court No. - 29
Case :- WRIT TAX No. - 1158 of 2018 Petitioner :- M/S Chandra Kishor Singh Govt. Contractor And General Order Supplier Respondent :- The Director, Construction And Design Services U P Jal Nigam And 4 Others Counsel for Petitioner :- Shailesh Kumar Shukla,Sheo Kinkar Singh Counsel for Respondent :- Pranjal Mehrotra
Hon'ble Pankaj Mithal,J. Hon'ble Saral Srivastava,J.
The petitioner is a contractor who has been granted a contract for construction of Officers Hostel in Police Line, Allahabad by the Construction and Design Services U.P. Jal Nigam, respondent no.4. The parties have entered into an agreement for the above purpose.
A dispute has arisen between the parties to the contract as to who is liable to pay GST on the value of the construction work done under the contract. The petitioner alleges that the liability to pay the GST is upon the respondents and not upon it.
The aforesaid dispute is one concerning the agreement between the petitioner and the respondents, which vide Clause 24 provides for resolution of such disputes by Arbitration.
In view of the aforesaid remedy available to the petitioner for seeking an arbitration, we are not inclined to interfere in the matter. The petition is accordingly dismissed on the ground of alternative remedy.
Order Date :- 21.8.2018 Ashutosh Pandey
Disclaimer: Above Judgment displayed here are taken straight from the court; Vakilsearch has no ownership interest in, reservation over, or other connection to them.
Title

M/S Chandra Kishor Singh Govt Contractor And General Order Supplier vs The Director

Court

High Court Of Judicature at Allahabad

JudgmentDate
21 August, 2018
Judges
  • Pankaj Mithal
Advocates
  • Shailesh Kumar Shukla Sheo Kinkar Singh