The grievance of the petitioner is that he has not been paid the amount due for the execution of the contract work pertaining to construction of bus stand shelters in front of Thiruvathipuram Bus Stand.
2.It appears that on the allegation made by a third party by name K.Senthil, a direction was issued by this Court, pursuant to which, an Enquiry Committee was constituted. A perusal of the report of the Committee would show that there is no substantial truth in the allegations made against the work completed by the petitioner. However, the said report is still pending consideration of the respondents.
3.Now there is some confusion as to whether who should take a final call among the respondents 1 and 2. Be that as it may. The writ petition stands disposed of by directing the respondents to pass appropriate orders on the question of releasing the remaining amount payable to the petitioner on consideration of the report submitted by the Enquiry Committee within a period of six weeks from the date of receipt of a copy of this order. No costs.
27.06.2017 Index:Yes/No mmi To
1.The Commissioner of Municipal Administration, Government of Tamil Nadu, Chepauk, Chennai - 5.
2.The Commissioner, Thiruvaththipuram Municipality, Thiruvaththipuram, Thiruvannamalai District.
M.M.SUNDRESH, J.
mmi W.P.No.9282 of 2017 27.06.2017 http://www.judis.nic.in
Disclaimer: Above Judgment displayed here are taken straight from the court; Vakilsearch has no ownership interest in, reservation over, or other connection to them.
Title

A.Ilangovan vs Commissioner Of Municipal ...

Court

Madras High Court

JudgmentDate
27 June, 2017