Judgments
Judgments
  1. Home
  2. /
  3. High Court Of Judicature at Allahabad
  4. /
  5. 1999
  6. /
  7. January

Abb Abl Limited And Others vs National Thermal Power ...

High Court Of Judicature at Allahabad|03 November, 1999

JUDGMENT / ORDER

JUDGMENT G.P. Mathur and Yatindra Singh, JJ.
1.This is a writ petition for a direction to the National Thermal Power Corporation Limited (NTPC) to rescind the decision taken by it in awarding the contract of Steam Generator Package for Talcher Super Thermal Power Project to Bharat Heavy Electrical Limited (BHEL) and to consider the case of M/s. Combustion Engineering Inc., (CE inc.) with ABB ABL Limited as the Indian assignee for granting of the said contract.
2. NTPC floated a global tender on 15th of December. 1997 for the supply and installation of (i) Steam Generator (SG) Package and (ii) Steam Turbine Generator (STG) Package as per the brief particulars specified in the bidding documents. In this writ petition, we are concerned with the supply and installation of Steam Generator (SG) Package only. There were three bidders and the bids were opened by NTPC on 2nd of December, 1998. Subsequently all bidders were given an opportunity to rectify the inconsistencies and were asked to submit fresh bids. This time only two parties, namely, CE Inc. and BHEL submitted their bids. They are respondent Nos. 4 and 5 in this writ petition. The bids were examined by a tender committee comprising of experts in the field. The bid of CE Inc. was found to be non-responsive and decision was taken to award the contract to BHEL. A letter of intent was issued to BHEL on 9th August, 1999 with some conditions. BHEL was to give its acceptance by 31st August, 1999. We are informed that BHEL has given such consent.
3. CE Inc. is a foreign bidder. Under the special condition of contract, a foreign bidder was to propose an Indian assignee. ABB ABL Limited (petitioner No. 1) is its Indian assignee. Petitioner Nos. 2 to 6 are the registered trade unions of ABB ABL Limited. Petitioner Nos. 2 to 6 filed a writ petition in the Calcutta High Court on 31st August, 1999 against the decision of NTPC to award the contract to BHEL. In this writ petition, initially ABB ABL Limited was a respondent but during the pendency of the same. ABB ABL Limited was transposed as a petitioner. The Calcutta High Court on the same day (31.8.1999) granted an ex parte interim order maintaining status quo with regard to award of contract to BHEL. This interim order was continued and ultimately the learned single Judge of the Calcutta High Court dismissed the writ petition on the ground that it did not have territorial jurisdiction but passed the following order :
"In view of that this interim order which has been passed is vacated, however no order as to costs. Accordingly this writ petition is also dismissed. Stay of the operation of the order as asked for, is granted for three weeks. Xerox certified copy of this order if applied for by the parties be supplied expeditiously on usual terms."
4. The present writ petition was filed before the Allahabad High Court and was taken up before a Division Bench on 27th October. 1999. The bench on that day heard Sri Shanti Bhushan learned senior counsel for the petitioner and on the request of Sri Sharad Varma learned counsel for BHEL adjourned it to 29th October, 1999. On this date, one of the members of the bench fell ill and did not come to the Court. The petitioners filed an application before Hon'ble the Chief Justice with a prayer to constitute a new bench to hear the matter on 30th October, 1999 as the matter was urgent and required an interim order before 31st October. 1999. On this application, Hon'ble the Chief Justice constituted the present bench to hear the case on 30th October. 1999. We had heard Sri Shanti Bhusan, Senior Advocate for the petitioner. Sri Dinesh Dwivedi counsel for NTPC and Sri J.C. Seth and Sri Sharad Varma counsel for BHEL on that day.
5. Learned counsel for the respondents have raised three preliminary objections for the maintainability of the writ petition. We will first deal with these preliminary objections. The first preliminary objection is about the territorial jurisdiction of the Allahabad High Court. This objection is two fold : (i) The draft contract which was also circulated contains a condition that all dispute will be subject-matter to Delhi Courts only. It is only the Delhi High Court which has jurisdiction to entertain this writ petition, (ii) The decision to award the contract to BHEL was taken at Delhi and no part of cause of action has arisen in Uttar Pradesh. The Allahabad High Court has no territorial Jurisdiction to entertain this writ petition.
6. The first objection about territorial jurisdiction relates to a term in the draft contract. No contract has been entered into by the parties. The counsel for the respondents concede that there was no clause in the advertisement limiting the dispute to Delhi Courts only. The term in the draft contract will govern the parties after the contract is entered into and any dispute arising thereafter. The dispute in the present writ petition is whether the contract should be awarded to BHEL or not? The term in the draft contract cannot oust the jurisdiction of this Court. The Allahabad High Court will have jurisdiction to entertain this writ petition if a part of cause of action has arisen in Uttar Pradesh. Let us consider whether any part of cause of action has arisen in Uttar Pradesh or not?
7. The global tender was issued by NTPC on 15th December, 1997 (Annexure-2 to the writ petition). Paragraphs 3 and 6 of the same are relevant and are quoted below :
"3. Interested eligible bidders may obtain further information from and inspect bidding documents at the office of :
DGM (Contract Services ER-TSTP).
According to these conditions, interested persons could have obtained information brochure and the documents at the office of NTPC at NOIDA (U. P.) and were also required to submit these documents at the office of NTPC at NOIDA (U. P.). These documents in the present case were obtained at NOIDA and were also submitted there. It is a part of cause of action. It cannot be said that the part of cause of action has not arisen in Uttar Pradesh.
8. The second preliminary objection is that the writ petition is premature as merely a letter of intent has been issued and as no contract has been entered into with BHEL. The petitioners have annexed bidding documents for the project (part of Annexure-3 to the writ petition). This is divided into different sections. Section 1 of this document is 'invitation for bids' (IFB). Section 2 of this document is 'instruction to bidders (ITB). Sub-section (E) of ITB gives details of 'bid opening and evaluation'. Paragraph 22 prescribes Preliminary Examination of Bids', paragraph 23 details 'Conversion to single currency', paragraph 24 prescribes Technical evaluation' and paragraph 25 talks about 'Commercial evaluation' of the bid. After evaluation of the bids contract is to be awarded and this is mentioned in sub-section (F) of ITB namely 'Award of Contract'. The paragraph 29 of the sub-section (F) talks about 'Award criteria' and states that Employer will award a contract to successful bidder whose bid has been determined to be substantially responsive. The counsel for the respondents have admitted that bids of the parties have been evaluated by the experts under these provisions. They have submitted a report on 4.8.1999. The bid of the CE Inc. was found to be non-responsive. This report was approved by the Chairman of the NTPC on 6th August, 1999 and by the Board of Directors on 9th August, 1999 and then the letter of intent has been issued to BHEL on the same day. Once the bid of CE Inc. was found to be non-responsive, i.e., to say, it was rejected and it was decided to award the contract to BHEL, a letter of intent was issued on 9th August. 1999 with some conditions seeking their acceptance and BHEL has given its consent, then writ petition cannot be termed as premature. The NTPC has taken a decision not to award the contract to CE Inc. and to award it to BHEL. The writ petition is not premature, it cannot be rejected on this ground.
9. The third preliminary objection is that the petitioners do not have any legal right to maintain this writ petition. If there is any right, it is only with CE Inc. (respondent No. 4) and not with the petitioners. In order to understand this preliminary objection, it is necessary to consider the 'Special condition of the contract' (part of Annexure-3 to the writ petition] mentioned at serial Nos. 30.1 to 30.4 :
"30.1. The contracts to be entered into with the successful bidder shall be as under :
For Foreign Bidder
--'First contract' for CIF/CIP supply of all offshore equipments and materials including mandatory spares :
--'Second contract' for Ex-works supply of all equipments and materials including mandatory spares of Indian origin and for providing all services i.e. port handling and clearance for the imported goods, further loading and inland transportation for delivery at site, unloading, storage, handling at site, installation, testing and commissioning including performance. Testing in respect of all the equipment supplied under both the Contracts and any other services specified in the contract documents."
For Domestic Bidder
--'First contract' for Ex-works supply and CIF/CIP supply, if any, of all equipment and materials including mandatory spares identifying separagraphtely the CIF/CIP and Ex-works components of the supply.
--'Second Contract' for providing all services, i.e., inland transportation for delivery at site, unloading, storage, handling at site, installation, testing and commissioning including performance testing in respect of all the equipment supplied under the 'first contract' and any other services specified in the Contract Documents.
30.2. The award of two contract shall not in any way dilute the responsibility of the contractor for the successful completion of the facilities as per specifications and a breach in one contract shall automatically be construed as a breach of the other contract which will confer a right on the employer to terminate the other Contract also at the risk and the cost of the contractor.
30.3. If the foreign bidder has proposed an assignee in his bid to execute the second contract and has also furnished written unequivocal consent of the proposed assignee to work as independent contractor on the terms offered by the bidder and the employer is satisfied with experience qualification of the proposed assignee, the employer will enter into the second contract with the said assignee.
Further, the said assignee in addition to the contract performance security to be provided by the contractor for ten per cent (10% of the value of both contracts i.e.. first contract and second contract, shall provide within twenty eight (28) days of the notification of award, a contract performance security equivalent to ten per cent (10%) of the value of second contract for the due performance of contract with a validity upto sixth (60) days beyond the defect liability period. It is expressly understood and agreed that the both the contracts shall contain the aforesaid crossfall breach clause.
30.4. It is further expressly understood and agreed that in case the opinion is not exercised by the bidder or the assignee fails to enter into the second contract with the employer or if the Employer in its judgment does not find acceptance of the proposed, assignee as its contractor, then the bidder shall be obliged to enter into and execute both the contracts with the Employer and both contracts shall contain the aforesaid crossfall breach clause."
The special conditions of the Contract (30.1) envisage two contracts--first contract is for supply of all offshore equipment and materials including mandatory spares and the second contract is for Ex-works supply of all equipment and materials including mandatory spares of Indian Origin. The bidder. CE Inc. is a company based in USA. it is a foreign bidder. A foreign bidder (30.3) is also entitled to propose an Indian assignee to execute the second contract, This Indian assignee is subject to satisfaction of NTPC. ABB ABL Limited (petitioner No. 1) is proposed as a Indian assignee of CE Inc. It is not a bidder. It has no existence till the bid of CE Inc. is accepted and even then it is subject to the satisfaction of NTPC. If by not awarding the contract to CE Inc. the NTPC has acted unfairly or arbitrarily, then rights if any of CE Inc. are violated and not of ABB ABL Limited (petitioner No. 1). As a matter of fact under the special conditions of contract (30.3 and 30.4) even if bid of CE Inc. is accepted. NTPC is not bound to accept the proposed assignee. ABB ABL Ltd. would have come into existence if the contract was awarded to CE Inc. and the NTPC had approved the ABB ABL Ltd. as an Indian Assignee. Neither ABB ABL Ltd. has made any bid nor any of its rights have been violated, no writ petition at its instance is maintainable. Petitioner Nos. 2 to 6 are merely registered trade unions with ABB ABL Ltd.. none of their rights are being violated. They are also not entitled to maintain this writ petition.
10. Sri Shanti Bhusan senior counsel for the petitioners has argued that CE Inc. could not file this writ petition due to shortage of time and merely for this reason, this writ petition should not be thrown out. CE Inc. was a party before the Calcutta High Court and had engaged a counsel before the Calcutta High Court, supporting the case of the petitioner. There is no reason as to why it could not file a writ petition in this Court if it considers that it was wrongly dealt with. Petitioner No. 1 cannot proxy for CE Inc.
11. Sri Shanti Bhusan further argued that position of ABB ABL Limited is similar to the position of a joint bidder and if there was a joint bidder, then it would undoubtedly be entitled to maintain this petition. The petitioners, have also annexed the bidding documents for the Project (Part of Annexure-3 to the writ petition). Section 3 of the bidding documents is BID DATA SHEET (BDS). item No. 8 of BDS refers to 'Instruction to bidder' (ITB) clause, reference No. 9.3 (c) and (e). The Part II of the same (at page 109 of the writ petition) states that the joint ventures are not permitted. There cannot be any Joint bidder. ABB ABL Ltd. was neither a joint bidder, nor under the bidding documents it could be a joint bidder. It is an assignee who is yet to come into existence.
12. We have upheld the third preliminary objection of the respondents. It is sufficient to dismiss this writ petition. But this writ petition is for installation of Steam Generator costing more than thousand crores of rupees and relates to priority sector of power. The entire controversy relating to the award of contract should be decided at an early date. The learned counsel for the petitioner has also addressed us on the merit of the writ petition. In view of aforesaid, we consider it proper to express our views on the merits of award of contract to BHEL.
13. Sri Shanti Bhusan has challenged the award of contract to BHEL on four main grounds : (i) This contract was awarded to BHEL at the behest of Hon'ble Sri P. Kumarmanglam, Cabinet Minister for Power and is for extraneous considerations, (ii) The bid of CE Inc. was the lowest and ought to have been accepted by the NTPC. (iii) The Central Vigilance Commissioner has issued guidelines on 18th November, 1998 for improving vigilance administration. The NTPC has acted contrary to the guidelines and have entered into post-tender negotiations with persons other than lowest tenderer, viz., BHEL. (iv) BHEL has contacted NTPC and has thus breached paragraph 27 of the instructions to the bidders and its bid ought to have been rejected. We now deal with these submissions on the merits of the case.
14. The first submission on merits relates to mala fides alleged against Hon'ble Sri P. Kumarmanglam. Cabinet Minister for Power. In this regard. Sri Shanti Bhusan invited our attention to paragraph 9 and ground No. A to the writ petition. In this paragraph. It is mentioned that Hon'ble Sri Kumarmanglam announced in a public meeting held on 8th August, 1999 that Board of Directors will award the contract to BHEL on 9th August 1999. According to him, the only factory of BHEL which will get benefit is the Trichy Plant which was in his constituency and decision was taken at his behest. In support of this allegation, he also referred to various newspaper reports which are annexed as Annexure-7 to the writ petition. We do not find any merit in the submission for more than one reason. Firstly Hon'ble Sri P. Kumarmanglam is not made a party in the writ petition and no allegation of personal mala fide can be entertained without impleading him as a party- Secondly, it is a settled law that newspaper reports are not admissible (See Nageshwar Rao v. State of A.P., AIR 1959 SC 1376 at 1382 ; Laxmi Raj Shetty v. State of Tamil Nadu, AIR 1988 SC 1274 and Qamrul Islam v. S.K. Kanta, AIR 1994 SC 1733. Thirdly any statement made by Hon'ble Sri P. Kumarmanglam does not vitiate the decision taken by NTPC on the basis of the report of the experts on the evaluation of their bids. Some of the newspaper reports merely state that Hon'ble Sri P. Kumarmanglam had refuted the charge that he had shown favours to multinationals. Even if this statement is correct, it does not show any pressure by him on NTPC in awarding the contract to BHEL
15. Sri Shanti Bhusan in support of his second submission urged that the bid made by CE Inc. was for Rs. 1304 crores while the bid of BHEL was for Rs. 1382 crores and the bid of CE Inc. being lower, the NTPC should have awarded the contract to it. It is noteworthy that the contract has been awarded to BHEL after evaluation by the experts of NTPC who had examined the technical aspect of the bids made by the parties. The technical and financial evaluation of the bids had been done by the experts at several stages and after taking into consideration the deviation and variation of the price factor, the contract was awarded to BHEL. In a matter relating to construction and installation of Steam Generator for a Super Thermal Power Project involving huge investment, the cost alone cannot be the sole criteria and various technical aspects of the project have also to be taken into consideration. In any case the bid of the CE Inc. was found to be non-responsive. In such a matter, it is difficult for the Court to examine the merits of the bids submitted by the bidder, they being highly technical in nature. The bids have to undergo commercial and technical evaluation as detailed in the bidding documents. The bid of CE Inc. was found to be non-responsive. We have briefly mentioned the detailed procedure in paragraph 8 of the judgment. The Courts do not have expertise to go into technical and commercial evaluation of the bids and in view of the fact that no mala fide apart from the one already dealt with (paragraph 14 of the judgment) have been alleged, we see no reason to interfere with the decision taken by the NTPC in this regard.
16. The clause 30.1 of the bid document relates to employees right either to accept or reject any bid and it reads as follows :
"30.1. The employer reserves the right to accept or reject any bid and to annul the bidding process and reject all bids at any time prior to award of contract, without thereby incurring any, liability to the affected bidder or bidders or any obligation to Inform the affected bidder or bidders of the grounds for the employer's action."
The aforesaid clause in the bid document clearly shows that the NTPC has got the absolute right not to accept the lowest tender. A similar clause came into consideration in P.R. Quenim v. M.K. Tandel, AIR 1974 SC 651 and in paragraph 12 of the report it was held as under :
"A clause in tender for lease of distillery by which the Government reserves the right to select any tender or reject all tenders without assigning any reason therefor is not violative of Article 14. Thus, the Government is not bound to accept the tender of the person who offers the highest amount."
Similar view was taken in State of U.P. v. Vijay Bahadur Singh, AIR 1982 SC 1234 ; Union of India v. Hindustan Development Corporation, AIR 1994 SC 998 and Tata Cellular v. Union of India, AIR 1996 SC 11 (paragraphs 85 and 112). The same principle was reiterated in a recent decision rendered in Raunaq International Ltd. v. I.V.R. Construction Ltd., 1999 (1) SCC 493, where in paragraph 16 it was observed as under :
"It is also necessary to remember that price may not always be the sole criterion for awarding a contract. Often when an evaluation committee of experts is appointed to evaluate officers, the expert committee's special knowledge plays a decisive role in deciding which is the best offer price offered is only one of the criteria. The past record of the tenderers, the quality of the goods or services which arc offered, assessing such quality on the basis of the past performance of the tenderer, its market reputation and so on, all play an important role in deciding to whom the contract should be awarded. At times, a higher price for a much better quality of work can be legitimately paid in order to secure proper performance of the contract and good quality of work-which is as much in public interest as a low price. The Court should not substitute its own decision for the decision of an expert evaluation committee."
Therefore, the award of the contract of BHEL cannot be struck down merely on the ground that CE Inc. had made a bid for a lesser amount.
17. Sri Shanli Bhusan in support of his third submission has urged that after the bid had been made by BHEL the NTPC entered into negotiations with it and such a course of action was illegal. In view of the direction issued by the Central Vigilance Commission on 18th November, 1998. In this direction, it is mentioned that in order to avoid corruption post tender negotiations are banned with immediate effect except in the case of negotiations with 1.1 (i.e., lowest tenderer). The aforesaid direction purports to have been issued under Section 8 (1) (h) of Central Vigilance Commission Ordinance. 1998 which reads as under:
"Exercise superintendence over the vigilance administration of the various Ministries of the Central Government or Corporation established by or under any Central Act. Government Companies Societies and Local authorities owned or controlled by the Government."
In our opinion Section 8 (1) (h) of the Ordinance does not confer the jurisdiction upon the Central Vigilance Commission to issue binding direction. It is merely a guideline and does not have any statutory force and in this case, the bid of CE Inc. was rejected as being non-responsive leaving BHEL as the only bidder. The award of contract to BHEL cannot be nullified on the ground of violation of the guidelines issued by the Central Vigilance Commission especially in view of the fact that neither any illegal financial gratification has been alleged nor perhaps can be any when both companies are held by Central Government.
18. Sri Shanti Bhusan in support of his fourth submission has pointed out paragraphs 27.1 and 27.2 of the instruction of bidders (page 97 of the writ petition) which prohibits a bidder from contacting the employer on any matter relating to its bids from the time of the opening of bids to the time the contract is awarded. He also pointed out paragraph 6 of the writ petition where it is stated that BHEL have given some secret undertaking on 30.5.1999 that they are willing to match the price of the lowest bidder. According to him, the bid of BHEL should have been rejected as it has contacted NTPC.
19. Sri J.C. Seth learned counsel for the BHEL has submitted that after the first bid was opened on 2nd December, 1998, NTPC sent letters dated 20lh April, 1999 asking the parties to file revised bids complying with the NTPC documents. Thereafter the BHEL made a fresh bid and also wrote a letter on 30th May. 1999, wherein an offer was made that in case any other bidder quotes a lower price, they should first be given an opportunity to match the price taking into account domestic price preference as provided in the tender for domestic bidders. A copy of this letter was produced before us by the contesting respondents and was also shown to the learned counsel for the petitioners. This shows that BHEL did not breach paragraphs 27.1 and 27.2 of the institutions to the bidders.
20. The petitioners have assailed the award of contract to BHEL by means of the present writ petition under Article 226 of the Constitution. The award of the contract is purely administrative matter. The principles and the scope of enquiry in judicial review of an administrative action have been considered in Tata Cellular's case, (supra) and it has been observed that the modern trend points to judicial restraint while reviewing administrative decisions relating to contractual power of Government. Having given our careful consideration to the submissions made by the learned Counsel for the parties, we do not find that there has been any error in the decision making process relating to grant of contract by NTPC in favour of BHEL.
21. There is no merit in this petition. It is hereby dismissed. The interim order dated 30.10.1999 directing the parties to maintain status QUO is vacated.
Disclaimer: Above Judgment displayed here are taken straight from the court; Vakilsearch has no ownership interest in, reservation over, or other connection to them.
Title

Abb Abl Limited And Others vs National Thermal Power ...

Court

High Court Of Judicature at Allahabad

JudgmentDate
03 November, 1999
Judges
  • G Mathur
  • Y Singh